Vittal Mallya Road - Model Corridor Development
Objective: To support Prestige Constructions and UB Group along with other government stakeholders in the development of a model road project that can be replicated across the city.
Project Anchors:
V Gopal, Prestige Contructions
P S Anand, UB City.
Sequence of Activities:
September, 08 - Prestige Constructions Engineers presented the design proposal to the BCCF board.
Nov-Dec, 08 - The plans were reviewed by the T&T team. The challenge of addressing the utility requirements and facilitating inter-agency coordination was a task that BCCF T&T team carried out with the Prestige team.
Jan - June, 09 - The plans were presented at the BTTI meetings with the GoK to garner the support of BBMP and the other stakeholders.
September, 09 - On ground implementation begins.
Excavator work: Sept- Dec,2009Anchor Speak:
Mr. Gopal the Senior VP - Projects and Planning, Prestige Constructions
Highlighted the challenges of predicting underground assets. He acknowledged the value of having close coordination with multiple stakeholders such as the meetings that were organized.
He also pointed to the need for continued cooperation of multiple stakeholders in maintaining the stretch and utilizing the utility ducts as planned and agreed.
Progress Images
Before September, 09
September - December, 09

Shoulder drain work: Sept- Dec,2009